Guangdong Petrochemical Project Full-density Polyethylene Device Key Equipment Lifting

Home > Finance

Guangdong Petrochemical Project Full-density Polyethylene Device Key Equipment Lifting

2021-11-27 12:02:38 34 ℃

On November 25th, the Guangdong Petrochemical Integrated Project of Guangdong Petrochemical Integrated Project of Jieyang Binhai, the two products of the full-density polyethylene unit were smoothly located, marking the plane of the device's large-scale lifting work towards the sprint phase.

Lifting site. Liu Wenzhen photo

The full-density polyethylene device product degassing position is to complete the polyethylene resin powder in its internal, reach a safe and stable state, and the resin powder is delivered to the granulation system, with a weight of 245 tons, 45.5 meters high, and the vertebra The body has a maximum diameter of 6.94 meters, which falls on a concrete frame of up to 49.5 meters high, and the equipment is 75 meters later, which is the highest point of the full density polyethylene device.

Ultra-high equipment height and the design of the device are the biggest problem facing this hanging. In order to ensure the smooth lifting of the off-air, Guangdong Petrochemical Company's chemical production has organized a special meeting, and the lifting plan is discussed, the sand table, the work is attached, and finally the 1,600 tons of crawler cranes are the main crane, 400 Tons of crawler hang is a hike.

Before hoisting, the chemical production is two, the engineering management department and the units of the participating units have passed the sleeve, uninterrupted clears, so that the off-air warehouse will enter the preparatory position in advance. Under all consrsWers, the off-air warehouse "perfectly lifts".

[Reporter] Lin Jie Yong

[Correspondent] Feng Linsen

[Author] Lin Jie Yong